New Builder’s Lien Amendments & Regulations

May 30, 2017

Recent amendments to the Builder’s Lien Act and new Builders Lien Regulations, effective June 30, 2017, allow for early release of holdbacks to subcontractors and alter how finishing holdbacks are calculated. These changes are particularly helpful to subcontractors who finish their work at an earlier stage of a project.

Early Holdback Release

When a subcontractor completes their work on a project, they can request their contract be certified complete by the Project Consultant (or the owner and general contractor if there is no Project Consultant). When the subcontract is certified complete, the owner has 10 days to post a notice of subcontract completion on the public portion of the Construction Association of Nova Scotia website and in a prominent location in the job site office, if such office exists. The notice must include the name and address of the owner, contractor, subcontractor, and person on whose certificate payments are to be made, as well as a description of the work or services performed, a description of the land on which work was performed, and the date of certified completion. The owner can then release the portion of the holdback related to the subcontractor’s work 60 days after completion is certified.  This allows any lien rights related to the subcontractor’s work to expire.  The owner must also confirm that any liens regarding the subcontractor’s work have been satisfied, discharged, or vacated.

The regulations create an exception to the early release holdback for owners doing work on single-family residences owned or occupied by the owner or their spouse if the value of the work is $75,000 or less.

Finishing Holdback Calculation

Prior to the amendments, an owner was required to hold a finishing holdback of 2.5% of the overall project value. Now, if after 60 days from when the contract is deemed to be substantially performed, there are still services or materials needed to fully complete the contract, the owner is to maintain a 10% holdback of the price of the remaining services or materials to be supplied for completion. The finishing holdback must be held for 60 days after the project is 100% complete.

The regulations also create notice requirements following substantial completion of the contract. The owner has 10 days after the general contractor achieves substantial performance of the contract to post a notice of substantial performance on the public portion of the Construction Association of Nova Scotia website and in a prominent location in the job site office, if such office exists. The notice must include the name and address of the owner and contractor, a description of the work or services performed, a description of the land on which work was performed, and the date on which it was substantially completed.

Related Articles

Limiting Liability by Contract

Written by F. Richard Gosse. Background The concept is not new – parties committing to provide work or services decide to write down what each expects of the other: a scope of work, a mechanism for payment, some general provision for timelines, changes, and warranties or the like. More sophisticated engagements may (or may not) […]

read more

Construction Contracts & Why You Should Have One

An ounce of prevention is worth a pound of cure – particularly for construction. Whether it is a new build or a renovation, it is costly work prone to surprises. A properly drafted contract will benefit both the owner and the contractor by providing clarity and certainty. The contract should: Clearly define the scope of […]

read more
view all
Cox & Palmer publications are intended to provide information of a general nature only and not legal advice. The information presented is current to the date of publication and may be subject to change following the publication date.